ROAD PAVING & RECLAMATION August 17 - August 25

posted Aug 17, 2017, 5:50 AM by Jolene Bouchard   [ updated Aug 17, 2017, 5:55 AM ]
Pike Industries will be in Scarborough this week and next week to reclaim and pave roads.  This schedule is subject to change due to weather so check back from time to time.  If the schedule changes we will update our postings.

AUGUST 17:  Broadturn Rd and Martin Ave   Both roads will be reclaimed. The end result will be gravel-like material and the roads will stay this way until the following week.  Martin Ave is scheduled first and work will start at 7:00 am.  Broadturn Rd work will not start before 8:30 am but will last all day.  Alternate routes of travel are encouraged during this time.

AUGUST 18:  Woodside Drive  Scheduled for reclamation.  The end result will be a gravel-like material that will remain until the following week.

AUGUST 21:  Broadturn Road, Pine Point Road, Martin Ave  Paving & grading will occur.  Work will not start on Broadturn Road prior to 8:30 am but will continue into the early evening.  Alternate routes of travel are encouraged. 

AUGUST 22:  Broadturn Road and Martin Ave  Paving is scheduled to be completed. 


AUGUST 23:  Woodside Drive  Grading & paving scheduled all day.


AUGUST 24 & 25:  Both Days may be used to finish any work not done on prior days because of weather or other unforeseen circumstances.

Thank you for your patience and safe driving while this work is performed.  Alternate routes are recommended during this time if possible.