Pike Industries is scheduled for one more round of paving starting Wednesday, October 11, 2017.  The schedule is as follows if weath
er allows:

  • Wednesday, October 11 - Hearn Road (Saco town line to Ash Swamp Road)- Road grinding and grading - with paving scheduled for Tuesday, October 17
  • Thursday, October 12 -    Beaver Brook Road - Road grinding and grading  with paving scheduled for Tuesday, October 17
  • Wednesday, October 18 - Holmes Road (Beech Ridge Road to Mitchell Hill Road) paving only

 Thank you for your patience and safe driving while this work is performed. Please expect delays alternate routes are recommended during this time if possible.