Inspections
Types of Inspections
Provided below is a list of various inspection types and descriptions. For additional information, please contact Scarborough's Planning & Codes Department.
Inspection Type |
Description |
---|---|
Footing Inspection |
Performed after forms are in, before footings are poured; setbacks to property lines must be verifiable. |
Foundation Inspection
|
Performed after forms are in; bond outs and rebar installed. |
Backfill Inspection
|
Performed after forms are removed, damp proofing applied, perimeter drains, stone and filter fabric in place & before placement of backfill. |
On-site Subsurface Wastewater Disposal System
|
Minimum of 2 inspections – first at scarification of bed bottom; second when disposal bed, tank and distribution box, or pump station is installed but not buried. |
Internal Plumbing Inspections
|
Sub-slab piping installations prior to concrete pour; above grade rough-in; required test (air or water) must be on. |
Complete Rough-In Inspection
|
Includes the combined individual inspections for framing, plumbing and electrical rough-in prior to insulating and close-in. |
Framing Inspection
|
Performed after any electrical and plumbing is roughed in, and after all framing, fire-stopping, draft stopping and bracing are in place. |
Electrical Inspection
|
Performed prior to insulation and/or close-in. |
Electrical Temporary Service |
(one ground rod minimum) |
Electrical Permanent Service |
(two ground rods in place and panel is bonded) |
Insulation Inspection |
Insulation and air barrier; U-Value of windows; air sealing of all infiltration sources/penetrations in thermal envelope. |
Fire Separation in garage |
(required only if materials can not be verified at final) |
Final Inspection |
This inspection must receive final approval for the issuance of a Certificate of Occupancy (when required) before the space can be occupied or used. This is the official end of the building permit process. |