Low Impact Development (LID) Ordinance

Vegetated swale

 

The Town is developing a Low Impact Development (LID) Ordinance to help ensure that new development protects our natural resources.

What is Low Impact Development?

vegetated swale with runoff

Plants and soil in this vegetated swale will filter pollutants from runoff.

LID is a planning and stormwater management approach that works the way nature does. Instead of letting runoff wash directly into waterways, it encourages water to soak into the ground, where plants and soil filter out pollutants. The following are important elements of LID:

  • Preserve natural features, like wetlands, vegetation, and drainageways.
  • Use stormwater treatment systems that mimic nature, are smaller, and treat runoff close to the source.
  • Create fewer hard surfaces, like roads, rooftops, and parking lots (collectively called Impervious Cover, or IC).
     

Why We Need an LID Ordinance

Scarborough is one of the fastest-growing communities in Maine, and we have high-value natural resources, like the Scarborough Marsh, that must be protected. In addition, Scarborough and 29 other Maine communities are required to adopt LID standards as a condition of our federal Clean Water Act permit. The Maine Department of Environmental Protection (DEP) has set minimum standards that must be met.

Vision Statement 1 of the Comprehensive Plan also supports the ordinance:

The Scarborough Marsh is central to the Town’s identity, creating a special awareness by our residents of the importance of all of the Town’s natural resources. Future land use will follow a pattern of development that is sensitive to protecting our beaches, dunes, rivers, open spaces, farmlands, and other elements that comprise our unique ecosystem.

What's in the LID Ordinance?

Maine DEP has set minimum standards that Scarborough must adopt. Our ordinances already meet some of the requirements. The remaining standards will either be adopted without changes or enhanced to protect Scarborough Marsh, Urban Impaired Streams (Long Creek, Red Brook, and Phillips Brook), Threatened Streams (Mill Brook, Willowdale Brook, and Beaver Brook), and other water resources. Recommended enhancements are based on studies, policies, and feedback from advisory committees and community members.

Changes from DEP's minimum standard

Topic

Required Standard

Enhanced Standard

Applicability

 

Developments that disturb 1 acre of land or more

All sites subject to Site Plan or Subdivision approval, unless otherwise noted

Site Clearing

Natural Resource Buffer

25-foot vegetated buffer to natural resources

40-foot vegetated buffer plus an additional 10-foot setback to natural resources

Protect Drainageways

Culvert Crossings

New crossings of waters of the State use StreamSmart principles

New and replacement culverts meet either StreamSmart principles (freshwater streams) or CoastWise principles (tidal crossings)

Minimize Impervious Cover (IC):

Impervious Cover

Reduce IC using recommended strategies like multi-story building and parking structures

Set maximum IC per parcel based on the needs of the specific watershed

Road Width

Do not exceed local minimum road widths; waivers considered

Define allowable waivers and align waivers with Complete Streets Policy

Dead-end Streets

Optional: cap dead-end streets at 1,000 feet

Prohibit new public dead-end streets; cap private dead-end streets at 1,000 feet

Parking Spaces

Optional: cap spaces at 9x19 feet

Cap spaces at 9x18 feet; allow compact spaces

Minimize the Effect of Impervious Cover (IC)

New development with more than 20,000 sq ft impervious

Disconnect or treat at least 95% of impervious area and 80% of developed area, unless site constraints prevent it

No relief for site constraints in Urban Impaired and Threatened Stream watersheds

Pollutant Removal

Sites with >1 acre of disturbance: 80% removal of total suspended solids; 60% removal of total phosphorus and total nitrogen

Meet standard for all sites in Urban Impaired and Threatened Stream watersheds

Redevelopment with more than 20,000 sq ft IC

Disconnect or treat 30% of existing plus 100% of new impervious area, at the same pollutant removal rates above

Disconnect or treat 50% of existing plus 100% of new impervious area in Urban Impaired and Threatened Stream watersheds

Stormwater Treatment and Retention

Treatment Area Size

Each water quality treatment measure sized for <1 acre of impervious area, with an exception for institutional or commercial uses (including industrial uses)

Require maximum sizing for water quantity and quality facilities; waiver for industrial and institutional uses >1 acre and <3 acres.

Winter Maintenance & Snow Storage

Chloride (Winter Salt)

Consider chloride source control in Urban Impaired Stream watersheds

Require chloride source control in Urban Impaired and Threatened Stream watersheds

Anticipated Timeline

rain garden in parking lot

This rain garden collects runoff from the parking lot.

Goal: Ordinance adoption by July 1, 2027

March – December 2026

  • Staff develop language
  • Advisory committees review/provide feedback
  • Public feedback

January – February 2027

  • Ordinance Committee review

March – April 2027

  • Town Council first reading
  • Planning Board public hearing

May – June 2027

  • Town Council public hearing
  • Town Council second reading & vote

     