Pine Point Water Line Replacement

The Town is coordinating with Gorham Sand & Gravel and Maine Water on water main replacement work in Pine Point. Work will be conducted on:

  • Jones Creek Drive
  • Avenue 3
  • Avenue 4
  • Avenue 5 (section)
  • Avenue 6
  • King Street (section)

Phase I (January 26-February): Avenue 3

  • Road closed; local traffic only

Phase II (February-March): Avenue 4

  • Road closed; local traffic only

There will be no water service disruption for this initial work.

There is a July 1st completion deadline, with full paving work to follow in the fall of 2026 or spring of 2027.